JCT Clause 6.5.1 Insurance
Joint Contracts Tribunal (JCT) Clause 6.5.1 of the Standard Building Contract and Minor Works Contract places a requirement on the contractor to organise insurance both for themselves and the client.
This insurance provides cover should there be damage to a neighbouring property due to the works that are carried out, and the cause of which is not the result of negligence.
The case of ‘Gold v Fotheringham’ [1958] set the precedent that the employer of a contractor is responsible for any damage caused to third parties and may be liable to pay compensation.
The contractor will probably already be required to hold public liability insurance, as will an architect, along with professional indemnity insurance, but these policies only indemnify them if the damage has arisen from their own negligence. However, there may be damage with no clear negligence. For example, a neighbouring building may start subsiding a few weeks after demolition works have taken place correctly and professionally. The owner of the damaged building will likely be insured under their buildings policy, but those insurers will be keen to recover costs from another party, i.e. the employer of the contractor.
The insurance is generally obtained by the contractor on behalf of the employer, with both names on the policy. This is a requirement of the contract, and the contractor will include it within their quoted price to carry out the works as a whole. The employer will typically be responsible for both the premium and any excess payable in the event of a claim.
The risks that are covered are named within the JCT Contract as:
- Collapse.
- Subsidence.
- Heave.
- Vibration.
- Weakening or removal of support.
- Lowering of groundwater.
NB The insurance terms of JCT 2016 are found in Clause 6 and Schedule 3. There are five main types of insurance that may be required:
- Employers’ liability insurance – which protects against Employers' liability for injury of employees arising in connection with their employment (clauses 6.1 – 6.4 JCT 2016).
- Insurance against non-negligent withdrawal of support – which covers potential structural damage to neighbouring property caused by the withdrawal of support (clause 6.5).
- Insurance of the works and of existing structures – which covers physical damage to the works, site materials and existing structures (if there are any) (clauses 6.7 to 6.11 and Schedule 3 JCT 2016) – discussed in detail below.
- Public liability insurance – which covers liability arising from death or personal injury to, or damage to property belonging to, third parties (clauses 6.1 – 6.4 JCT 2016).
- Professional indemnity insurance – which insures against liability arising from professional negligence. Architects, engineers and other professional consultants that owe a design responsibility to the Employer are usually required to maintain such insurance (clauses 6.15 and 6.16 JCT 2016).
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Contractors’ all-risk insurance.
- Damage caused by construction works.
- Employer's liability insurance.
- Insurance.
- Joint names policy.
- Latent defects insurance.
- Making sure your builder has appropriate insurance.
- Professional Indemnity Insurance.
- Public liability insurance.
- Risk register.
- Run-off cover.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.